Major construction for Taber projects
Highway 3 twinning between Taber and Burdett
Alberta Transportation and Economic Corridors describes upgrading a 46 km section of Highway 3, from the Town of Taber to west of the Hamlet of Burdett, from a two-lane to a divided four-lane highway. Its schedule runs from minor bridge work in winter 2023 through subbase, gravel and paving in the summers of 2024 and 2025 to paving, signs, guardrail and intersection work in summer 2026, with Ledcor Highways Ltd. named as contractor. The page says major construction will take up to three years and gives no completion date, so confirm the current phase with the project owner. For a comparable highway job, identify the contractor's receiving base separately from the work limits, then discuss beds and washing facilities for the actual overnight rotation.
Source: Highway 3 twinning (Taber to Burdett), Government of Alberta, Transportation and Economic Corridors